Media Studio Progress

Currently the focus for the media studio is to complete everything that is required for drywall installation. Today the backdoor is being installed, which will reuse the previous door. The monks spent several days refurbishing the door and building the frame and blocking in which it will hang. The insulation began to go in today as well.