Iraivan Update – February 5th

Aum Namah Sivaya,

Today, our taskforcer Yajatadeva brings us some photos of Iraivan Temple's current progress. The siplis have finished the detail work on the yalli handrails and are now engaged in the joining work for the wall section that was above the recently removed earthen ramp. While that is taking place, some of the siplis are working on the details for the front steps which will go between the yallis. A new foundation piece has been poured in front of the temple to support the steps and the drain pipes along the outside of the foundation are being completed, which will allow for the lavarock wall to move forward. Aum.