October 3, 2013Currently the focus for the media studio is to complete everything that is required for drywall installation. Today the backdoor is being installed, which will reuse the previous door. The monks spent several days refurbishing the door and building the frame and blocking in which it will hang. The insulation began to go in today as well.

The completed door frame

The door is designed to ensure so no water will enter through it into the building

Kumarnathaswami work to instal the blocking for the door frame


These are the mango wood vents which will reside towards the bottom of the walls, creating much the building\
s ventilation'


The insulation installation begins


Brahmanathaswami works on installing soundproof insulation on the server room wall

every little space has to be filled with putty to avoid sound penetration
}
];