August 7, 2020Today we have a brief update for you of the progress on Iraivan Temple's lavarock wall and current stone carving work. Flip through the slideshow and enjoy! Aum.

The lavarock wall is now in full motion on the west side of the temple and is seeing rapid progress

On the east side, the stone laying is nearly complete.



There\
s only one full layer left to go'

On the north side of the temple, two full layers of stone have been placed

and on the afore mentioned west side, there is already one full layer


There was a concrete pour for this side just a few days ago

Of course, the west side already has the only completed section, which was done as an example

true to its name, the mossrock is already sprouting vibrant, green life

At the temple entrance we find the siplis making some finishing touches on the steps

They are \"sanding\" the tops, using a bumped, flat head chisel.



That includes some work on the faces of the steps as well


Until next time..