Iraivan's Temple Lavarock Update - September 20

Aum Namah Sivaya

A quick update to show us the progress on the lavarock wall along the eastern side of Iraivan Temple. To top layer of stones is gradually being completed. Following a taut string, which perfectly defines the top edge, each stone is hand selected to fit just right, and chiseled ever so slightly to get a perfect straight line all along the top of the lavarock face. These top stones have been completed along 1/3 of the eastern side of the temple.

Image

The southeastern corner of the temple lavarock has a full row of top stones in place

Image

Image

Image

Image

The top layer of stones will be filled in with concrete and a layer of stones behind what you see here

Image

As we move further down the wall (to the north) we reach some unfinished sections which are quickly progressing.

}

];