Rare Peek Inside Iraivan Floor Tile Project
November 13, 2022Today was a day off for the busy tile setting team, so we took the opportunity to sneak inside the workspace to see what they've been up to.
Some of their tools are organized in this tent next to Nandi Mandapam
They just finished pouring what they call the \"float\" around three sides of the temple-- a sloped mortar bed on which the granite tiles will be placed so they automatically slant toward the water drains
One of two 50-ft strong tents recently erected to keep the rain off
Mortar bed
And we have the first set of granite tiles laid down here in the northeast corner.
The narrow granite strips on the left start at the same level as the large tiles but then slope downwards toward the drain
One of many water drains set beautifully in a small granite square tile
}
];