Granite Tile Installation Forging Ahead

The team installing the Iraivan floor in the second prakaram is gaining momentum. It has taken weeks to map out the puzzle (65 different sizes of tile) and prepare the surfaces. And now tiles are going down. Even today, which is Saturday, the team is on the job, pushing hard, arriving at 6:30am in the dark to get a quick start on the day. See a retro slideshow that goes back to tile arrival and floor prep.

Image

From this morning (12\/3)

Image

Tiles arrive and are offloaded.

Image

Image

Arumuganathaswami oversees the project, guiding the initial storage of the pallets.

Image

A pallet is moved up on the temple floor.

Image

In the background Larry carefully brings the heavy tiles to the floor.

Image

Image

This pallet jack is just the right tool.

Image

Strapping the next pallet for larry

Image

Up and away...

Image

Slowly

Image

And down gently

Image

Here we see the options of grout color

Image

We chose the one on the left

Image

Nice match.

Image

Cutting into the floor to provide additional drainage pipes that will be hidden.

}

];