A contractor team has arrived to begin two to three weeks of work to create a concrete road around Iraivan Temple, replacing the temporary crushed asphalt we have there now. Some time after they are done, another team will cover the road with quartzite tile. Besides allowing vehicles to conveniently drive around, the road can serve as a circumambulation path for pilgrims doing sadhana, and occasional parades.
Today the main focus was to dig out the area that will connect the stairs coming up the hill to the temple granite staircase, where more technical precision is needed to ensure that the eventual quartzite tile layer will be at just the right height next to the first granite stair. They will pour this area on its own first, then the rest of the road later.
Auspiciously, today also happened to be the monthly Gurudeva Chitra pada puja.
Also, we continue to have a flock of nene geese moving about the property.